After years of planning and preparation, next month marks the official start of construction for the Holland Energy Park! Find our anticipated timeline for completion below. Get updates on progress or join in the conversation by following us on Facebook.
Estimated Dates | Tasks |
---|---|
January 1, 2015 | Contract signed by all parties |
February 16, 2015 | Site mobilization |
April 2015 | Groundbreaking |
July 20, 2015 | Combustion Turbine Generator delivery |
August 17, 2015 | Heat Recovery Steam Generator (HRSG) delivery |
August 31, 2015 | Steam Turbine Generator delivery |
January 25, 2016 | Building structural steel complete |
September 19, 2016 | First fire |
November 3, 2016 | First steam |
December 17, 2016 | Target substantial completion |
February 15, 2017 | Guaranteed substantial completion |